Elevator Installation & Acceptance Inspection Checklist

이 체크리스트는 영어로 제공됩니다.

An acceptance inspection checklist for verifying a newly installed elevator meets ASME A17.1 safety code before it is placed in service.

ASME A17.1 / CSA B44ASME A17.2IBC 2021 Ch. 30NEC 620

무료 PDF 또는 Word · 이메일을 입력하면 다운로드할 수 있습니다.

Documentation & Permits

  • Is the elevator installation permit and approved layout drawing on site? *
  • Is the manufacturer's data plate and rated load/speed posted in the car? *
  • Are wiring diagrams and maintenance control program (MCP) documents available? *

Machine Room & Hoistway

  • Are machine room clearances, lighting, and disconnect means compliant? *
  • Is the hoistway free of unrelated piping/ducts and properly enclosed/vented? *
  • Are pit access, ladder, stop switch, and clearances verified? *
  • Are guide rails, buffers, and counterweight properly installed? *

Car & Doors

  • Do hoistway and car door interlocks and restrictors function correctly? *
  • Is the door reopening (safety edge / detector) device operational? *
  • Are car emergency lighting, alarm, and two-way communication working? *
  • Is the car leveling within tolerance at each landing? *

Safety & Firefighter Service

  • Have car and counterweight safeties and the overspeed governor been tested? *
  • Has Phase I and Phase II firefighters' emergency operation been tested? *
  • Does emergency/standby power operation function as designed? *

Load Test & Sign-Off

  • Has a full rated-load and (where required) overload test been performed? *
  • Has the traction/rel/leveling been verified under load? *
  • Is the acceptance test witnessed and certified by the AHJ/QEI inspector? *
  • Acceptance date