Documentation & Readiness

  • Are approved structural drawings, the mix design, and placing drawings on site? *
  • Is the special inspector present and the pre-placement inspection scheduled before concrete arrives? *
  • Are prior test reports (rebar mill certs, mix design approval) available? *
  • Has the formwork/rebar been cleaned of ice, mud, oil, and loose scale? *

Reinforcing Steel Placement

  • Do bar sizes, grades, and quantities match the structural drawings? *
  • Is bar spacing within the specified tolerance? *
  • Are lap splice lengths and locations correct for the bar size and class? *
  • Are hooks, bends, and development lengths per the drawings? *
  • Is reinforcing adequately tied and supported to prevent displacement during placement? *

Concrete Cover & Clearances

  • Is minimum concrete cover maintained for the exposure condition? *
  • Are chairs, bolsters, and spacers of the correct height and spacing? *
  • Is clear spacing between parallel bars adequate for aggregate passage? *

Embedments & Formwork

  • Are anchor bolts, embed plates, and sleeves located and secured per drawings? *
  • Are conduit and pipe embedments within allowable size and spacing limits? *
  • Is formwork tight, braced, and of correct dimension and grade line? *
  • Are construction and control joint locations per the drawings? *
  • Photo of placed reinforcement prior to pour