Design & Approval Documentation
- Are approved sprinkler and fire alarm shop drawings on site? *
- Are hydraulic calculations and water supply data available for the sprinkler system? *
- Does the installed occupancy hazard classification match the design basis? *
- Is the AHJ notified in advance of the acceptance test? *
Sprinkler System Installation
- Are sprinkler head types, temperature ratings, and spacing correct for the hazard? *
- Are clearances to obstructions and deflector-to-ceiling distances compliant? *
- Are hangers, bracing, and seismic restraints installed where required? *
- Is the fire department connection (FDC) accessible and labeled? *
- Are spare sprinklers and a wrench provided in the spare cabinet? *
Sprinkler Testing
- Has the underground and aboveground piping passed a 200 psi hydrostatic test for 2 hours? *
- Have underground mains been flushed at the required flow rate? *
- Has the main drain (flow) test been performed and readings recorded? *
- Has the inspector's test connection actuated the waterflow alarm within 90 seconds? *
Fire Alarm System
- Are all initiating and notification devices installed per approved plans? *
- Have 100% of installed devices been functionally tested? *
- Is audible/visible notification (candela, dBA) verified in occupied areas? *
- Has off-site monitoring/supervising station signal transmission been confirmed? *
- Is secondary (battery) power capacity verified for the required standby period? *
Commissioning & Records
- Is the contractor's material and test certificate completed and signed? *
- Is a record (as-built) drawing set provided to the owner? *
- Are operation and maintenance manuals delivered? *