AIAG CQI-9 Heat Treat System Assessment Checklist

A checklist based on the AIAG CQI-9 Special Process: Heat Treat System Assessment, covering management responsibility, pyrometry, process monitoring, and equipment for automotive heat-treat operations.

AIAG CQI-9IATF 16949:2016

Free PDF · enter your email to download.

Management & Job Audits

  • Is a heat treat system assessment (HTSA) completed at least annually and signed by management? *
  • Are job audits performed to verify parts are processed to the applicable specification and control plan? *
  • Are operator qualifications and training records maintained for heat-treat personnel? *

Pyrometry (Section 3)

  • Is system accuracy testing (SAT) performed at the required frequency for each control/recording instrument? *
  • Are temperature uniformity surveys (TUS) conducted at the required frequency for each qualified furnace? *
  • Are thermocouple types, usage limits, and calibration/replacement intervals controlled per the thermocouple table? *
  • Is the instrumentation type (A-E) correctly assigned to each furnace and documented? *

Process Monitoring & Tables

  • Are process parameters (temperature, time, atmosphere/carbon potential, quench) recorded and within the process table limits? *
  • Is quenchant condition monitored (temperature, concentration, agitation, cooling curve) per the quench requirements? *
  • Are alarms and reaction plans in place for out-of-limit process excursions? *

Equipment & Laboratory

  • Is preventive maintenance performed on furnaces, quench systems, and pyrometry equipment? *
  • Are metallurgical test methods (hardness, microstructure, case depth) validated and equipment calibrated? *
  • Record furnace ID(s) assessed and next TUS/SAT due dates