A field inspection checklist for exterior insulation and finish systems and continuous air barriers covering water-resistive barrier, flashing, insulation, and continuity.

ASTM E2568ASTM E2570ASTM E2357IBC 2021 Ch. 14IECC 2021

Free PDF · enter your email to download.

Substrate & Water-Resistive Barrier

  • Is the sheathing sound, dry, and fastened per the manufacturer's requirements? *
  • Is a water-resistive barrier installed continuously and lapped shingle-fashion? *
  • Is a drainage/water-managed EIFS provided where required? *
  • Are penetrations and transitions sealed to the WRB? *

Flashing & Terminations

  • Are back-wrapped edges and terminations detailed at all openings? *
  • Is through-wall and window/door flashing integrated with the WRB? *
  • Are sealant joints provided at dissimilar materials and expansion joints? *
  • Is minimum clearance to grade and horizontal surfaces maintained? *

Insulation & Lamina

  • Is the insulation board type, thickness, and attachment per the listing? *
  • Are board joints tight, staggered, and rasped flush? *
  • Is reinforcing mesh fully embedded in the base coat with proper overlap? *
  • Is the finish coat applied at the specified thickness and cure conditions? *

Air Barrier Continuity

  • Is the air barrier material continuous across the assembly and detailed at transitions? *
  • Are seams, laps, and fasteners sealed per the manufacturer? *
  • Where required, has whole-building or assembly air leakage testing been performed? *
  • Photo of WRB, flashing, and mesh embedment